Getting Started - Quick Start Guide / Workflow | Send comments on this topic |
1Create Civil 3D® Catchments and associate them to relevant structures of the branch being analyzed. See Civil 3D documentation on how to create and work with Catchments.
ØCatchment information, Properties, and Runoff methods can be set using the standard C3D catchment properties window.
ØRunoff Method should be set to "Rational and Modified Rational Method". This is the industry standard when performing EGL/HGL (Standard Step Method, or HEC22 method).
2Create/Set up Pipe Network(s). See Civil 3D documentation.
ØEnsure that pipe properties are set up correctly. Example of typically missed item: Pipe Manning Coefficient. This property is often overlooked and left to a default value which may not necessarily match the pipe material. The design engineer must ensure that this and other relevant values are set correctly.
▪See the "Extra Editing Tools" for setting the Manning Coefficient for multiple pipes at a time, plus other useful batch process tools
3Create IDF Curve Information for the current drawing.
4Run the H.AT. Base Dialog or the H.A.T. Palette Version to get started.
5IMPORTANT: Set the location of the "Raw" calculation file (.json file). This is crucial since leaving the default location (a user's TEMP folder) is used otherwise. Setting a location that is accessible by all team members will prevent any unnecessary access issues.
6Select the rain event. Only the events defined in the IDF Curve Creation are listed.
7Select a branch to analyze. A branch is defined by any number of pipes and structures that are connected. Any storm sewer gravity network can contain multiple branches. Therefore, you can analyze one branch at a time as you proceed with your design.
8Set the start WSE. Select from the standard Crown, Normal, or Critical options, or manually enter the starting WSE if known.
9Run the analysis. If the branch contains pipes that do not have any flow, the analysis is stopped. This only happens if there are pipes at the upstream end that do not have reference catchments and therefore contribute zero flow. At a minimum, the most upstream structures require flow in order to propagate flows from upstream to downstream. See exception for edge cases below.
ØHowever, if you wish to "disconnect" upstream sections, as would the case when connecting downspouts (or downspout systems) from large buildings and you wish to associate a catchment representing the roof area at the structure where the downspout system connect; the calculation engine detects this and continues. In this case, ensure that "last" upstream structure (or the "first" structure if looking in the opposite direction) has flow.
ØSee illustrations of the "Edge" Cases below: